T
yonlu 6ce0661fca chore: complete v1.0 Consolidation milestone
Archive milestone artifacts:
- milestones/v1.0-ROADMAP.md (full roadmap archive)
- milestones/v1.0-REQUIREMENTS.md (26/26 requirements complete)
- milestones/v1.0-phases/ (8 phase directories with plans, summaries, verifications)

Updated:
- PROJECT.md: full evolution review, all consolidation requirements validated
- ROADMAP.md: collapsed to milestone summary with archive link
- STATE.md: reset for next milestone
- MILESTONES.md: created with stats and accomplishments
- RETROSPECTIVE.md: created with lessons learned

Deleted:
- REQUIREMENTS.md (archived, fresh for next milestone)

8 phases, 17 plans, 34 tasks, 84 tests added, 6 days
2026-03-05 09:34:43 -05:00

77 lines
5.5 KiB
Markdown
Raw Blame History

This file contains ambiguous Unicode characters
This file contains Unicode characters that might be confused with other characters. If you think that this is intentional, you can safely ignore this warning. Use the Escape button to reveal them.
# Project Retrospective
*A living document updated after each milestone. Lessons feed forward into future planning.*
## Milestone: v1.0 — Consolidation
**Shipped:** 2026-03-05
**Phases:** 8 | **Plans:** 17 | **Tasks:** 34
**Timeline:** 6 days (2026-02-27 → 2026-03-05)
### What Was Built
- Race-free concurrency across all 4 SetContext entry points
- Honest error handling: startupErr to struct, config permissions, MPRIS logging, scan warning separation
- 84 unit tests covering queue, config, player, FTS5 search, library scan, entity cache
- SQL consolidation: track_metadata VIEW, sqlc.slice() migration, SAFETY comments on 12 hand-crafted queries
- AST-based Go→TypeScript event codegen with pre-commit enforcement
- Incremental queue persistence (O(1) add/remove) and SetQueue Phase 2 dedup
- Deferred library store loading for instant app shell
- Frontend design token system, classMap directives, queueMicrotask coalescing
- Visual consistency audit across all 15 components
### What Worked
- **Dependency-ordered phases:** Fixing races → building test infra → writing tests → refactoring → performance → UX created a clean progression where each phase built on the last
- **Characterization tests before refactoring:** Writing tests in Phase 4-5 before SQL consolidation in Phase 6 caught zero regressions — the tests were accurate safety nets
- **Small, focused plans:** 2-3 tasks per plan kept execution fast and context fresh — most plans completed in under 10 minutes
- **Research phase for SQL consolidation:** Phase 6 research validated sqlc + VIEW + FTS5 compatibility before planning, avoiding mid-execution discovery
- **Internal package tests:** Testing queue/library as package-internal (not `_test` suffix) gave access to unexported fields for thorough state verification
### What Was Inefficient
- **Phase 8 repeat() regression:** Migrating virtualizers to `repeat()` directive in Plan 02 broke virtualization (repeat as child content bypasses lit-virtualizer's DOM management). Required a hotfix (72ef719) reverting to `.renderItem` + `.keyFunction`. Research should have caught this API distinction.
- **Task count tracking:** STATE.md only tracked tasks-per-plan for later phases (5-8), making total task count harder to derive at milestone completion
- **No startup time measurement:** TODO to measure startup time before Phase 7 lazy loading was never done — can't quantify the improvement
### Patterns Established
- **Mutex-protected setter pattern:** Lock → write field → release lock → call callbacks (prevents deadlock from callback re-entry)
- **ScanWarning + addWarning pattern:** Mutex-protected warning collection for non-fatal errors during long-running operations
- **applyPRAGMAs shared function:** Single source of truth for SQLite PRAGMAs, shared between production NewDB and test NewTestDB
- **SAFETY comment convention:** Two-part format (why + safety assurance) for hand-crafted SQL that bypasses sqlc
- **AST-based codegen over regex:** go/ast + go/parser for cross-language constant synchronization
- **Design token CSS custom properties:** `--yj-icon-sm/md/lg`, `--yj-text-xs/sm/md/lg/xl` scoped to `:host` in Lit components
- **queueMicrotask coalescing:** Batch multiple synchronous store notifications into single subscriber update
### Key Lessons
1. **Test the API contract, not the implementation surface:** repeat() inside lit-virtualizer looks correct syntactically but violates the component's rendering contract. Always verify how a library expects to be consumed, not just what compiles.
2. **Research before planning pays off immediately:** Phase 6 research confirmed sqlc + VIEW compatibility, saving mid-execution discovery and potential re-planning.
3. **Incremental persistence is O(complexity) not O(code):** The incremental queue persistence (Phase 7) was conceptually simple but required careful position-shift SQL for insert/remove operations — more thought than code.
4. **Design tokens must precede visual consistency work:** Phase 8 correctly defined tokens in Plan 01 before applying them in Plan 04 — reversing this order would have required double work.
5. **Contentless FTS5 has deletion limitations:** Cannot DELETE from tables with `content=''`. Document this in tests rather than fighting it — stale entries are harmless for the use case.
### Cost Observations
- Model mix: Primarily opus for planning + execution, sonnet for research
- Total commits: 107 across 6 days
- Notable: Plans averaging 2-6 minutes execution time; Phase 8 Plan 04 (visual audit across 15 components) was the longest at 8 minutes
- Efficiency: 17 plans × ~5 min avg = ~85 min total execution time for 34 tasks across 67 source files
---
## Cross-Milestone Trends
### Process Evolution
| Milestone | Days | Phases | Plans | Key Change |
|-----------|------|--------|-------|------------|
| v1.0 | 6 | 8 | 17 | First milestone — established GSD workflow, research-before-plan pattern |
### Cumulative Quality
| Milestone | Tests Added | Total Tests | Key Quality Win |
|-----------|-------------|-------------|-----------------|
| v1.0 | 84 | 84 | From 0 backend tests to comprehensive coverage of queue, config, player, database, library |
### Top Lessons (Verified Across Milestones)
1. Dependency-ordered phases (fix → test → refactor → optimize) prevent rework and ensure each phase builds on a stable foundation
2. Small plans (2-3 tasks, <10 min) maintain consistent quality — no context degradation
3. Research phases for unfamiliar domains (sqlc + VIEW, lit-virtualizer API) prevent mid-execution surprises