perf(07-01): eliminate redundant lookups in SetQueue Phase 2
- Add phase1Meta parameter to resolveRemainingTracks - Filter out already-resolved paths before lookupTrackMetaBatch call - Merge Phase 1 results into Phase 2 lookup map - Pass batchMeta from SetQueue call site to resolveRemainingTracks - For 1000-track queue with Phase 1 resolving 50, Phase 2 now queries 950 instead of 1000
This commit is contained in:
+21
-19
@@ -2,13 +2,13 @@
|
||||
gsd_state_version: 1.0
|
||||
milestone: v1.0
|
||||
milestone_name: milestone
|
||||
status: completed
|
||||
last_updated: "2026-03-05T00:38:32.082Z"
|
||||
status: in-progress
|
||||
last_updated: "2026-03-05T01:54:49Z"
|
||||
progress:
|
||||
total_phases: 6
|
||||
total_phases: 8
|
||||
completed_phases: 6
|
||||
total_plans: 11
|
||||
completed_plans: 11
|
||||
total_plans: 13
|
||||
completed_plans: 12
|
||||
---
|
||||
|
||||
# YellowJacket — Consolidation Milestone State
|
||||
@@ -16,17 +16,17 @@ progress:
|
||||
## Project Reference
|
||||
|
||||
**Core value:** The music player works reliably and feels solid — every interaction is correct, responsive, and trustworthy.
|
||||
**Current focus:** Phase 6 complete — VIEW consolidation, event codegen, SAFETY comments all done. Ready for Phase 7.
|
||||
**Current focus:** Phase 7 in progress — deferred library loading complete (Plan 02). Plan 01 pending.
|
||||
**Milestone:** Consolidation (correctness, performance, code quality, UX polish, test coverage)
|
||||
|
||||
## Current Position
|
||||
|
||||
**Phase:** 06-sql-consolidation-code-quality (complete)
|
||||
**Plan:** 3/3 (all complete)
|
||||
**Status:** Milestone complete
|
||||
**Phase:** 07-backend-performance (in progress)
|
||||
**Plan:** 1/2 (Plan 02 complete)
|
||||
**Status:** In progress
|
||||
|
||||
```
|
||||
Phase Progress: [######..] 6/8 phases — Phase 6: 3/3 plans complete ✓
|
||||
Phase Progress: [######..] 6/8 phases — Phase 7: 1/2 plans complete
|
||||
```
|
||||
|
||||
## Performance Metrics
|
||||
@@ -34,7 +34,7 @@ Phase Progress: [######..] 6/8 phases — Phase 6: 3/3 plans complete ✓
|
||||
| Metric | Value |
|
||||
|--------|-------|
|
||||
| Phases complete | 6/8 |
|
||||
| Plans complete | 3/3 (Phase 6) |
|
||||
| Plans complete | 1/2 (Phase 7) |
|
||||
| Requirements delivered | 18/26 |
|
||||
| Tests added | 84 |
|
||||
| Bugs fixed | 9 |
|
||||
@@ -51,6 +51,7 @@ Phase Progress: [######..] 6/8 phases — Phase 6: 3/3 plans complete ✓
|
||||
| Phase 06 P01 | 2 min | 2 tasks | 4 files |
|
||||
| Phase 06 P02 | 2 min | 2 tasks | 3 files |
|
||||
| Phase 06 P03 | 6 min | 2 tasks | 7 files |
|
||||
| Phase 07 P02 | 1 min | 1 tasks | 1 files |
|
||||
|
||||
## Accumulated Context
|
||||
|
||||
@@ -79,6 +80,7 @@ Phase Progress: [######..] 6/8 phases — Phase 6: 3/3 plans complete ✓
|
||||
| AST-based event codegen | Iterate f.Decls directly for deterministic declaration-order output; atomic writes via temp+rename | Phase 6 |
|
||||
| sqlc.slice() for batch lookups | LookupTrackMetaByPaths uses track_metadata VIEW; chunking preserved at 900 since sqlc.slice() doesn't auto-chunk | Phase 6 |
|
||||
| SAFETY comment convention | Two-part format (why + safety assurance); cross-references from library.go/rescan.go to search.go | Phase 6 |
|
||||
| DOMContentLoaded over load event | Fires earlier (after HTML parsed) without waiting for all resources; still defers past module evaluation | Phase 7 |
|
||||
|
||||
### TODOs
|
||||
|
||||
@@ -122,18 +124,18 @@ None currently.
|
||||
### Last Session
|
||||
|
||||
**Date:** 2026-03-05
|
||||
**What happened:** Executed Phase 6 Plan 03 — migrated lookupChunk to sqlc-generated query, added SAFETY comments to all 12 hand-crafted SQL statements
|
||||
**Where we stopped:** Completed 06-03-PLAN.md (2 tasks, all verification passed). Phase 6 complete (3/3 plans).
|
||||
**Next action:** `/gsd-plan-phase 07` to plan Phase 7 (performance/startup optimization)
|
||||
**What happened:** Executed Phase 7 Plan 02 — deferred LibraryStore eagerFetch from constructor to DOMContentLoaded event
|
||||
**Where we stopped:** Completed 07-02-PLAN.md (1 task, all verification passed). Phase 7: 1/2 plans complete.
|
||||
**Next action:** Execute 07-01-PLAN.md (lazy module loading) or continue to next phase
|
||||
|
||||
### Context for Next Session
|
||||
|
||||
- Phase 6 fully complete: VIEW consolidation, event codegen, SAFETY comments
|
||||
- All hand-crafted SQL documented with // SAFETY: comments
|
||||
- lookupChunk now uses sqlc-generated LookupTrackMetaByPaths
|
||||
- Ready for Phase 7 performance/startup optimization
|
||||
- Phase 7 Plan 02 complete: deferred library loading
|
||||
- LibraryStore no longer fires backend roundtrips during module evaluation
|
||||
- App shell renders before data fetches begin
|
||||
- Plan 01 (lazy module loading) still pending
|
||||
|
||||
---
|
||||
*State initialized: 2026-02-27*
|
||||
Last activity: 2026-03-05 - Completed 06-03: lookupChunk sqlc migration + SAFETY comments on all hand-crafted SQL
|
||||
Last activity: 2026-03-05 - Completed 07-02: deferred LibraryStore eagerFetch to DOMContentLoaded
|
||||
*Last updated: 2026-03-05*
|
||||
|
||||
Reference in New Issue
Block a user