docs(01-01): complete SetContext race fixes plan
- Created 01-01-SUMMARY.md with execution results - Updated STATE.md with Phase 1 completion and decisions - Updated ROADMAP.md progress (Phase 1: 1/1 plans complete) - Marked CORR-01 through CORR-04 complete in REQUIREMENTS.md
This commit is contained in:
+23
-19
@@ -3,28 +3,29 @@
|
||||
## Project Reference
|
||||
|
||||
**Core value:** The music player works reliably and feels solid — every interaction is correct, responsive, and trustworthy.
|
||||
**Current focus:** Roadmap created, awaiting Phase 1 planning.
|
||||
**Current focus:** Phase 1 complete, ready for Phase 2 planning.
|
||||
**Milestone:** Consolidation (correctness, performance, code quality, UX polish, test coverage)
|
||||
|
||||
## Current Position
|
||||
|
||||
**Phase:** — (not started)
|
||||
**Plan:** — (not started)
|
||||
**Status:** Roadmap complete, ready for phase planning
|
||||
**Phase:** 01-concurrency-race-fixes (complete)
|
||||
**Plan:** 1/1 (complete)
|
||||
**Status:** Phase 1 complete, ready for Phase 2 planning
|
||||
|
||||
```
|
||||
Phase Progress: [........] 0/8 phases complete
|
||||
Phase Progress: [#.......] 1/8 phases complete
|
||||
```
|
||||
|
||||
## Performance Metrics
|
||||
|
||||
| Metric | Value |
|
||||
|--------|-------|
|
||||
| Phases complete | 0/8 |
|
||||
| Plans complete | 0/? |
|
||||
| Requirements delivered | 0/26 |
|
||||
| Phases complete | 1/8 |
|
||||
| Plans complete | 1/1 (Phase 1) |
|
||||
| Requirements delivered | 4/26 |
|
||||
| Tests added | 0 |
|
||||
| Bugs fixed | 0 |
|
||||
| Bugs fixed | 4 |
|
||||
| 01-01 duration | 11 min |
|
||||
|
||||
## Accumulated Context
|
||||
|
||||
@@ -37,10 +38,13 @@ Phase Progress: [........] 0/8 phases complete
|
||||
| Tests before refactoring | Research unanimously recommends characterization tests as safety net | Phase 4-5 → 6-7 |
|
||||
| SQL consolidation after DB tests | FTS5 search tests verify VIEW doesn't change ranking | Phase 5 → 6 |
|
||||
| Frontend last | Backend API should be stable before frontend adapts | Phase 8 |
|
||||
| Release mutex before Wails runtime calls | Library/Playlist SetContext releases lock before registerEventHandlers/migrateExistingPlaylists to avoid blocking | Phase 1 |
|
||||
| Player SetContext single-lock | Collapsed double-lock to prevent partially-initialized observable state | Phase 1 |
|
||||
|
||||
### TODOs
|
||||
|
||||
- [ ] Plan Phase 1 (next step)
|
||||
- [x] Plan Phase 1 (complete)
|
||||
- [x] Execute Phase 1 Plan 01 (complete)
|
||||
- [ ] Validate sqlc + SQLite VIEW + FTS5 compatibility during Phase 6 planning (research flag)
|
||||
- [ ] Design queue test architecture during Phase 4 planning (research flag)
|
||||
- [ ] Determine library scan test fixture strategy during Phase 5 planning (research flag)
|
||||
@@ -60,18 +64,18 @@ None currently.
|
||||
|
||||
### Last Session
|
||||
|
||||
**Date:** 2026-02-27
|
||||
**What happened:** Project initialized — codebase analysis, research, requirements definition, roadmap creation
|
||||
**Where we stopped:** Roadmap created with 8 phases covering 26 requirements
|
||||
**Next action:** `/gsd-plan-phase 1` to create execution plan for Concurrency Race Fixes
|
||||
**Date:** 2026-02-28
|
||||
**What happened:** Executed Phase 1 Plan 01 — added mutex protection to all SetContext methods across Queue, Library, Playlist, and Player
|
||||
**Where we stopped:** Completed 01-01-PLAN.md (all tasks, verification passed)
|
||||
**Next action:** `/gsd-plan-phase 2` to create execution plan for Backend Correctness
|
||||
|
||||
### Context for Next Session
|
||||
|
||||
- All 26 v1 requirements mapped across 8 phases
|
||||
- Dependency chain: correctness → test infra → tests → SQL/perf optimization → frontend
|
||||
- Phase 1 is 4 requirements (CORR-01 to CORR-04), all mechanical mutex additions
|
||||
- Research says Phase 1 fixes are "textbook race, LOW effort" — standard patterns, skip research-phase
|
||||
- Phase 1 complete: all SetContext data races eliminated (CORR-01 through CORR-04)
|
||||
- All four packages pass `go test -race`, `go vet`, `golangci-lint` with 0 issues
|
||||
- Library and Playlist gained struct-level mutexes; Queue and Player already had them
|
||||
- Ready for Phase 2 (Backend Correctness) — error handling, config permissions, MPRIS errors
|
||||
|
||||
---
|
||||
*State initialized: 2026-02-27*
|
||||
*Last updated: 2026-02-27*
|
||||
*Last updated: 2026-02-28*
|
||||
|
||||