docs(07-01): complete queue persistence optimization plan
- SUMMARY.md with incremental persistence + Phase 2 dedup details - STATE.md updated: Phase 7 complete (2/2 plans), decisions recorded - ROADMAP.md updated: Phase 7 marked complete - REQUIREMENTS.md: PERF-01, PERF-02 marked complete
This commit is contained in:
+21
-18
@@ -3,12 +3,12 @@ gsd_state_version: 1.0
|
||||
milestone: v1.0
|
||||
milestone_name: milestone
|
||||
status: in-progress
|
||||
last_updated: "2026-03-05T01:54:49Z"
|
||||
last_updated: "2026-03-05T01:58:48Z"
|
||||
progress:
|
||||
total_phases: 8
|
||||
completed_phases: 6
|
||||
completed_phases: 7
|
||||
total_plans: 13
|
||||
completed_plans: 12
|
||||
completed_plans: 13
|
||||
---
|
||||
|
||||
# YellowJacket — Consolidation Milestone State
|
||||
@@ -16,25 +16,25 @@ progress:
|
||||
## Project Reference
|
||||
|
||||
**Core value:** The music player works reliably and feels solid — every interaction is correct, responsive, and trustworthy.
|
||||
**Current focus:** Phase 7 in progress — deferred library loading complete (Plan 02). Plan 01 pending.
|
||||
**Current focus:** Phase 7 complete — incremental queue persistence (Plan 01) and deferred library loading (Plan 02) both done. Ready for Phase 8.
|
||||
**Milestone:** Consolidation (correctness, performance, code quality, UX polish, test coverage)
|
||||
|
||||
## Current Position
|
||||
|
||||
**Phase:** 07-backend-performance (in progress)
|
||||
**Plan:** 1/2 (Plan 02 complete)
|
||||
**Status:** In progress
|
||||
**Phase:** 07-backend-performance (complete)
|
||||
**Plan:** 2/2 (all complete)
|
||||
**Status:** Phase 7 complete
|
||||
|
||||
```
|
||||
Phase Progress: [######..] 6/8 phases — Phase 7: 1/2 plans complete
|
||||
Phase Progress: [#######.] 7/8 phases — Phase 7: 2/2 plans complete ✓
|
||||
```
|
||||
|
||||
## Performance Metrics
|
||||
|
||||
| Metric | Value |
|
||||
|--------|-------|
|
||||
| Phases complete | 6/8 |
|
||||
| Plans complete | 1/2 (Phase 7) |
|
||||
| Phases complete | 7/8 |
|
||||
| Plans complete | 2/2 (Phase 7) |
|
||||
| Requirements delivered | 18/26 |
|
||||
| Tests added | 84 |
|
||||
| Bugs fixed | 9 |
|
||||
@@ -51,6 +51,7 @@ Phase Progress: [######..] 6/8 phases — Phase 7: 1/2 plans complete
|
||||
| Phase 06 P01 | 2 min | 2 tasks | 4 files |
|
||||
| Phase 06 P02 | 2 min | 2 tasks | 3 files |
|
||||
| Phase 06 P03 | 6 min | 2 tasks | 7 files |
|
||||
| Phase 07 P01 | 5 min | 2 tasks | 2 files |
|
||||
| Phase 07 P02 | 1 min | 1 tasks | 1 files |
|
||||
|
||||
## Accumulated Context
|
||||
@@ -81,6 +82,8 @@ Phase Progress: [######..] 6/8 phases — Phase 7: 1/2 plans complete
|
||||
| sqlc.slice() for batch lookups | LookupTrackMetaByPaths uses track_metadata VIEW; chunking preserved at 900 since sqlc.slice() doesn't auto-chunk | Phase 6 |
|
||||
| SAFETY comment convention | Two-part format (why + safety assurance); cross-references from library.go/rescan.go to search.go | Phase 6 |
|
||||
| DOMContentLoaded over load event | Fires earlier (after HTML parsed) without waiting for all resources; still defers past module evaluation | Phase 7 |
|
||||
| Incremental persistence for single-item mutations | Single-track add/remove use INSERT/DELETE + position shift; bulk ops keep full rewrite | Phase 7 |
|
||||
| Hand-crafted SQL for variable-N position shift | sqlc ShiftQueuePositionsUp only shifts by 1; variable-N needs raw UPDATE with SAFETY comment | Phase 7 |
|
||||
|
||||
### TODOs
|
||||
|
||||
@@ -124,18 +127,18 @@ None currently.
|
||||
### Last Session
|
||||
|
||||
**Date:** 2026-03-05
|
||||
**What happened:** Executed Phase 7 Plan 02 — deferred LibraryStore eagerFetch from constructor to DOMContentLoaded event
|
||||
**Where we stopped:** Completed 07-02-PLAN.md (1 task, all verification passed). Phase 7: 1/2 plans complete.
|
||||
**Next action:** Execute 07-01-PLAN.md (lazy module loading) or continue to next phase
|
||||
**What happened:** Executed Phase 7 Plan 01 — incremental queue persistence helpers and SetQueue Phase 2 dedup
|
||||
**Where we stopped:** Completed 07-01-PLAN.md (2 tasks, all verification passed). Phase 7 complete (2/2 plans).
|
||||
**Next action:** `/gsd-plan-phase 08` to plan Phase 8 (frontend polish)
|
||||
|
||||
### Context for Next Session
|
||||
|
||||
- Phase 7 Plan 02 complete: deferred library loading
|
||||
- LibraryStore no longer fires backend roundtrips during module evaluation
|
||||
- App shell renders before data fetches begin
|
||||
- Plan 01 (lazy module loading) still pending
|
||||
- Phase 7 fully complete: incremental persistence + deferred loading
|
||||
- Queue mutations (add/remove/insert) no longer rewrite entire table
|
||||
- SetQueue Phase 2 skips already-resolved paths from Phase 1
|
||||
- Ready for Phase 8 (frontend polish)
|
||||
|
||||
---
|
||||
*State initialized: 2026-02-27*
|
||||
Last activity: 2026-03-05 - Completed 07-02: deferred LibraryStore eagerFetch to DOMContentLoaded
|
||||
Last activity: 2026-03-05 - Completed 07-01: incremental queue persistence + SetQueue Phase 2 dedup
|
||||
*Last updated: 2026-03-05*
|
||||
|
||||